Stamford Hill Estate project update

We are currently completing flat roof replacements, decorations, concrete & brickwork repairs to three blocks (Berwyn, Brecon & Arran house) on the Stamford Hill Estate for Southern Housing.  To date, the scaffold has been fully erected on the three blocks, with roof replacement works completed on Berwyn and Brecon House, and redecoration to the to the masonry bands and walkway soffits in progress. Roof replacement works are progressing well at Arran House.

The new flat roofing being installed is a Langley specification, consisting of a 3-layer felt system along with a liquid coating compound being applied to certain areas. The existing crumbling render to the internal parapet wall has been renewed and any loose copings have been refixed. The tank room timber doors are being replaced with a prefinished metal to increase durability and remove the need for future cyclical work.

Before photos:

View of the top canopy roof area
Ponding water on the roof
Crumbling render to parapet wall
Saturated insulation to the roof

Related Posts

News

PROJECT UPDATE | ORION GATE, STEVENAGE

Great progress continues at Orion Gate in Stevenage, where our re-roofing works for Places for People are now nearing...

News

CONSTRUCTING EXCELLENCE AWARD FOR HARLOW

We are incredibly proud to share that Chas Berger has won the Constructing Excellence East of England Awards 2026...

News

PROJECT WIN | FRA & REFURB WORK, 9 TOWER BLOCKS, HARLOW

We are excited to announce that Chas Berger has been awarded the Fire Risk Assessment (FRA) and Refurbishment Works...