Project Update Linklea Close, Home Group
We are at 10 – 51 Linklea Close, having started on site in January. The project has progressed well and remains on track for timely completion


Externally, roof and gutter repairs have been carried out, along with rerouting of downpipes, drainage improvements, installation of bird deterrents and securing of fascias and soffits.
Internally, we have undertaken fire safety upgrades including fire door replacement and overhauls, application of Class ‘0’ fire-resistant paint in communal areas and extensive fire stopping.
Within the flats, upgrades have included damp treatment, redecoration, flooring repairs, window overhauls and kitchen and bathroom improvements. Communal areas have been deep cleaned, door entry systems repaired and stair nosings inspected. Electrical testing is currently being finalised across the block.
We look forward to completing the project and handing back a fully refurbished and safe building.
Stay tuned for more updates as we complete this important transformation for the Linklea Close community.
Related Posts
Appointment to the GFP DPS
We’re delighted to share that Chas Berger has been successfully appointed to the Greener Futures Partnership Dynamic Purchasing System...
Harlow Rugby Club Champions
We’re delighted to sponsor Harlow Rugby Club’s Women’s and Girls’ teams, including the Ladies 1st XV and the Girls...
Chas Berger Achieves BSA Accreditation Under Constructionline
We’re delighted to announce that Chas Berger is now accredited for the Building Safety Act (BSA) under Constructionline –...
